Maryland opened Megawatts for Maryland, a grant auction up to 100 million dollars in FY27. Stage 1 closes November 30. Awards are not operating megawatts.

The short version

No. The program is a competitive grant auction. Stage 1 closes November 30, 2026. Stage 2 bids are due January 22, 2027. Awards are expected in spring 2027.

The program

Governor Wes Moore announced Megawatts for Maryland on October 26, 2026. The Maryland Energy Administration administers it under the Utility RELIEF Act. The FOA for FY27 was issued the same day. The purpose is to offset development and construction costs for grid-scale renewable generation and storage through a closed competitive auction. The two-year envelope is up to 200 million dollars from the Strategic Energy Investment Fund. FY27 is up to 100 million. FY28 is anticipated at another 100 million. PV Tech carried the launch on October 28. A grant award is not a plant that is online.

The calendar

Stage 1 applications close at 3:00 p.m. Eastern on November 30, 2026. Stage 2 bids close at 3:00 p.m. Eastern on January 22, 2027. MEA anticipates award notices in spring 2027. Until those dates pass, the document is an open auction, not a list of winners. The Samsung SDI box agreement was a supply contract with a delivery year. This auction is a state grant process with later commercial-operation windows measured in years, not days. The document named in the sources is the record this page will keep.The SDI supply agreement.

What can win

Eligible activities include Tier 1 renewable generation that is not on net metering, storage co-located with Tier 1 sources, stand-alone storage, and hybrid generation-plus-storage projects. The bidder must be the entity that will sign the grant. Project sponsors can help, but they do not sign. Net-metering projects that sit outside the Tier 1 grid-scale lane stay out of this FOA. The Citicore loan was financing. This page is a grant auction. The document named in the sources is the record this page will keep. The document named in the sources is the record this page will keep.The Citicore loan.

Lowest bid per megawatt-hour

MEA ranks eligible bids by the requested price per megawatt-hour and awards the lowest. The bid calculator turns a unit price into a lifetime grant amount. That arithmetic is the program's. This page will not paste the spreadsheet. A reader who wants the formula has the FOA attachments. Canada's fleet-average rule was a model-year standard. Both filings stop where the public document stops. Asked directly, Who can bid? Businesses developing grid-scale Tier 1 renewable generation, energy storage, or hybrid projects that meet the program rules. The document named in the sources is the record this page will keep.Canada's fleet average.

Who is in scope

Developers who can meet the business and project rules, and Maryland ratepayers who are told the program is meant to add generation and lower costs. The governor's release says the aim is hundreds of megawatts and power for more than 150,000 homes per year. That aim is a program goal. It is not a meter reading. Heron's capacity claim was equipment that was not online. The same restraint applies to auction marketing. The document named in the sources is the record this page will keep.Heron's capacity.

The LG MoU is a different paper

LG Energy Solution's Energix MoU, filed beside this brief, is a company-to-company exploration of storage supply. Maryland's auction is a state grant process. They share a desk because both are energy documents dated this week. They do not share a counterparty. Asked directly, How much money does the state put on the program? Up to 200 million dollars over two fiscal years, with up to 100 million anticipated for FY27 and another 100 million anticipated for FY28. The document named in the sources is the record this page will keep.The Collie contract.

What this page will not invent

This page will not invent a winner list, a site list, or a commercial-operation date for a project that has not bid. The FOA is open. The wire account is PV Tech. The primaries are the governor's release and the MEA page. Asked directly, What is Stage 1? A preliminary application that establishes eligibility to bid. The deadline is 3:00 p.m. Eastern on November 30, 2026. Asked directly, How will MEA pick winners? MEA says it will award grants to eligible bidders requesting the lowest price per megawatt-hour from the closed auction.

The MBTA order stays a purchase

The MBTA order was a vehicle purchase with diesel still in the mix. A Maryland grant auction is a different kind of energy document. Linking it keeps the desk from treating every headline as generation already delivered. The short answer this page will stand on is this: No. The program is a competitive grant auction. Stage 1 closes November 30, 2026. Stage 2 bids are due January 22, 2027. Awards are expected in spring 2027. The document named in the sources is the record this page will keep.The MBTA order.

The record

The record is the October 26 governor release, the MEA program page and FOA, and PV Tech's October 28 account. Stage 1 closes November 30. Stage 2 closes January 22, 2027. Awards are expected in spring 2027. Online megawatts wait on later filings. DTE's Fish Creek park is a separate operating plant on a different desk filing, not a Maryland auction award. Asked directly, What is Stage 2? Eligible Stage 1 applicants submit a binding bid price and more documents by 3:00 p.m. Eastern on January 22, 2027.Fish Creek online.

Sources

The reports this brief is filing. Futureweb did not republish them.

  1. Governor Moore
  2. MEA program page
  3. PV Tech

Questions

How much money does the state put on the program?

Up to 200 million dollars over two fiscal years, with up to 100 million anticipated for FY27 and another 100 million anticipated for FY28.

What is Stage 1?

A preliminary application that establishes eligibility to bid. The deadline is 3:00 p.m. Eastern on November 30, 2026.

What is Stage 2?

Eligible Stage 1 applicants submit a binding bid price and more documents by 3:00 p.m. Eastern on January 22, 2027.

Who can bid?

Businesses developing grid-scale Tier 1 renewable generation, energy storage, or hybrid projects that meet the program rules.

How will MEA pick winners?

MEA says it will award grants to eligible bidders requesting the lowest price per megawatt-hour from the closed auction.